ACCOMPLISHED THIS WEEK

  • Drywall spackling finished in Connector.
  • Road and Parking lot was fine graded in preparation for paving.
  • Siding patching and replacement continued.
  • Safe framing to be finished and drywalled.
  • Rocks removed from vacant lot and area prepped for the election.
  • Town Hall was cleaned and voting booths set up for election.

NEXT WEEK

  • Town Hall exterior walls to be insulated.
  • Parking lot paving.
  • Connector drywall to be prime painted.
  • Heat to be installed.

SCHEDULED.

  • Connector flooring to be rescheduled to week of November 18th