 TOWN HALL PROJECT UPDATE – WEEK 9

ACCOMPLISHED THIS WEEK

  • Finished forming wall pockets and stone veneer ledge.
  • Poured concrete walls.
  • Striped concrete wall forms.

NEXT WEEK

  • Install perimeter insulation.
  • Start final grading the crawl space, mechanical room and Connector floors.

SCHEDULED.

  • Finish final grading the crawl space, mechanical room and Connector floors.
  • Install floor slab insulation and vapor barrier.
  • Pour the concrete “rat” slab, mechanical room slab and Connector slab.
  • Repair/replace floor beams and floor joists per architect’s details.
  • Building to be lowered once the concrete walls have cured and the floor joist system repairs are completed. (July)