TOWN HALL PROJECT UPDATE – WEEK 9
ACCOMPLISHED THIS WEEK
- Finished forming wall pockets and stone veneer ledge.
- Poured concrete walls.
- Striped concrete wall forms.
NEXT WEEK
- Install perimeter insulation.
- Start final grading the crawl space, mechanical room and Connector floors.
SCHEDULED.
- Finish final grading the crawl space, mechanical room and Connector floors.
- Install floor slab insulation and vapor barrier.
- Pour the concrete “rat” slab, mechanical room slab and Connector slab.
- Repair/replace floor beams and floor joists per architect’s details.
- Building to be lowered once the concrete walls have cured and the floor joist system repairs are completed. (July)