 TOWN HALL PROJECT UPDATE – WEEK 7

ACCOMPLISHED THIS WEEK

  • The remaining large rocks were removed.
  • Building footers excavated. (see picture)
  • Concrete contractor mobilized and are forming footers. (see picture)
  • Met with architect and detailed the scope of work required to fix the floor joist system.

NEXT WEEK

  • Pour footer concrete.
  • Set forms for concrete foundation walls.

SCHEDULED.

  • Pour concrete walls. (Mid-May)
  • Install crawl space perimeter insulation once concrete walls are poured and forms striped.
  • Final grade the crawl space floor then pour the concrete “rat” slab.
  • Repair/replace floor beams and floor joists per architect’s details.
  • Building to be lowered once the concrete walls have cured and the floor joist system repairs are completed. (July)