TOWN HALL PROJECT UPDATE – WEEK 6, April 22, 2024
ACCOMPLISHED THIS WEEK
- Finished the Connector demo and waterproofed the adjoining Library and Creativity Lab walls.
- Protected the Town Hall scenery drapes and secured the support structure. (see picture)
- Building lifted. Large rocks were removed. (see pictures)
NEXT WEEK
- The remaining large rocks are to be removed.
- Building footer excavation.
- Concrete contractor to mobilize in preparation of pouring footers.
- Meeting architect to determine the scope of work needed to fix the floor joist system.
SCHEDULED.
- Form and pour concrete walls once footers are poured. (Mid-May)
- Install crawl space perimeter insulation once concrete walls are poured and forms striped.
- Final grade the crawl space floor then pour the concrete “rat” slab.
- Building to be lowered once the concrete walls have cured and the floor joist system repairs are completed. (July)



