Wilmot Town Hall Update – Week 6, April 22, 2024

TOWN HALL PROJECT UPDATE – WEEK 6, April 22, 2024

ACCOMPLISHED THIS WEEK

  • Finished the Connector demo and waterproofed the adjoining Library and Creativity Lab walls.
  • Protected the Town Hall scenery drapes and secured the support structure. (see picture)
  • Building lifted. Large rocks were removed. (see pictures)

NEXT WEEK

  • The remaining large rocks are to be removed.
  • Building footer excavation.
  • Concrete contractor to mobilize in preparation of pouring footers.
  • Meeting architect to determine the scope of work needed to fix the floor joist system.

SCHEDULED.

  • Form and pour concrete walls once footers are poured. (Mid-May)
  • Install crawl space perimeter insulation once concrete walls are poured and forms striped.
  • Final grade the crawl space floor then pour the concrete “rat” slab.
  • Building to be lowered once the concrete walls have cured and the floor joist system repairs are completed. (July)
Meghan Foley