ACCOMPLISHED THIS WEEK
- Town Hall electric upgrades continued.
- Started to install Connector door hardware.
- Restrooms are operational. Some finishes remain for the next 2 weeks.
- Drywall in Safe area installed
NEXT WEEK
- Drywall in Safe area to be finished and painted.
- Restroom remaining finishes.
- Remove temporary restrooms
- Finish Library punch list items.
- Finish wall insulation.
SCHEDULED.
- Handicap ramp to be installed. (Now in Spring due to weather)
- NOTE: Town Hall tasks are scheduled to be finished, area cleaned and ready for use the week of January 6th. A notice will be sent for posting on the Town Website.