Wilmot Town Hall update – week 31 – October 15, 2024

TOWN HALL PROJECT UPDATE – WEEK 31

ACCOMPLISHED THIS WEEK

  • Finished roofing at Mechanical Room and flat area over Library extension.
  • Insulated Connector.
  • Regraded around buildings.
  • Removed blacktop and regraded parking lot. (see picture)
  • Installed on-demand HWH and manifold piping. (see picture)

NEXT WEEK

  • Complete Connector electric rough-ins.
  • Install drywall in Connector.
  • Install underground conduit for future generator.
  • Install loam on disturbed areas.
  • Install new walls at old Safe area.

SCHEDULED.

  • Parking lot and N. Wilmot Road paving scheduled for October 28th & 29th.  Road closure possible.
  • Connector flooring (November 11th – 13th)
  • NOTICE: The electrical contractor was not responding to scheduling needs and has been replaced. Therefore, the restrooms will not be completed for the upcoming November 5th election. The temporary restrooms will remain.

Meghan Foley