ACCOMPLISHED THIS WEEK

  • Temporary electric outlets installed for use by the construction contractors.
  • Continued selective demolition of the Connector to identify Creativity Lab electric wiring.
  • Removed snow from Site…again.

NEXT WEEK

  • Remove restroom fixtures and pressure tank. (rescheduled due to snow)
  • Start demolition to remove the Safe and Connector.
  • Reconnect Library lighting circuits that were fed from the Connector subpanel.
  • Protection and securing of the Town Hall scenery drapes. (awaiting confirmation)

SCHEDULED.

  • The propane tank is to be disconnected, emptied and tank removed by Irving Propane. New tank to be installed later. (Rescheduled due to 2nd snowstorm, date not yet confirmed by Irving)
  • Raising Town Hall sequence to start first week in May. (maybe sooner)