Wilmot Town Hall update – week 19 – July 22, 2024

TOWN HALL PROJECT UPDATE – WEEK 19

ACCOMPLISHED THIS WEEK

  • Foundation backfilling finished to rough grade elevations.
  • Perimeter drain installed.
  • Reinstallation of restored windows started. (see picture)
  • Grade raised at front door for easier access. (NOTE: The slope is steep until the parking area is raised, see picture)
  • New well supply pipe from well casing to the Connector installed.
  • Electric service line reconnected to building.

NEXT WEEK

  • Finish reinstalling windows.
  • Connector floor area will be graded and insulated in preparation for the concrete floor slab.
  • Patch lifting beam pockets.
  • Start the final floor system repairs.

SCHEDULED.

  • Pour Connector floor.
  • Install Connector framing and Library roof tie-in. (August)
  • Refinish Town Hall floor. (August)

NOTE: As planned, the Town Hall and Creativity Lab should be ready to be used for the September 10th Primary Election. However, the Connector finishes will not be completed at that time, therefore Portable restrooms will be available for Poll workers and Library staff use.  