TOWN HALL PROJECT UPDATE – WEEK 15
ACCOMPLISHED THIS WEEK
- Started repair/replacement of floor beams and floor joists per architect’s details.
NEXT WEEK
- Finish repair/replacement of floor beams and floor joists.
SCHEDULED.
- Move Library shelving and layout new pathway to the Connector.
- Building to be lowered once the concrete walls have cured and the floor joist system repairs are completed. (Possibly 2nd week in July)
- Patch lifting beam pockets.
- Finish floor system repairs.
- Reinstall windows.
- Install Connector framing and Library roof tie-in. (August)
- Refinish Town Hall floor. (late August)