TOWN HALL PROJECT UPDATE – WEEK 13
ACCOMPLISHED THIS WEEK
- Installed underfloor plumbing piping in Connector.
- Poured foundation wall left out for equipment access. (see picture)
- NOTE: Due to a concrete pump truck scheduling delay, the crawl space floor will not be poured until next Friday
NEXT WEEK
- Pour Crawl Space floor (rat slab)
- Move Library shelving and layout new pathway to the Connector.
SCHEDULED.
- Repair/replace floor beams and floor joists per architect’s details.
- Building to be lowered once the concrete walls have cured and the floor joist system repairs are completed. (July)
- Install Connector framing and Library roof tie-in. (August)
- Refinish Town Hall floor. (late August)