Wilmot Town Hall Update – Week 13, June 10, 2024

 TOWN HALL PROJECT UPDATE – WEEK 13

ACCOMPLISHED THIS WEEK

  • Installed underfloor plumbing piping in Connector.
  • Poured foundation wall left out for equipment access. (see picture)
  • NOTE: Due to a concrete pump truck scheduling delay, the crawl space floor will not be poured until next Friday

NEXT WEEK

  • Pour Crawl Space floor (rat slab)
  • Move Library shelving and layout new pathway to the Connector.  

SCHEDULED.

  • Repair/replace floor beams and floor joists per architect’s details.
  • Building to be lowered once the concrete walls have cured and the floor joist system repairs are completed. (July)
  • Install Connector framing and Library roof tie-in. (August)
  • Refinish Town Hall floor. (late August)
Meghan Foley
Leave a Reply

Find It Fast

ARE YOU IN?

Join us for email updates