Wilmot Town Hall Update – Week 12 – June 3, 2024

 TOWN HALL PROJECT UPDATE – WEEK 12

ACCOMPLISHED THIS WEEK

  • Finished final grading in mechanical room floor.
  • Finished installing floor beam support columns.
  • Installed crawl space sump pump and piping.
  • Installed crawl space floor vapor barrier and insulation.

NEXT WEEK

  • Install underfloor plumbing piping in Connector.
  • Final grade Connector Room floor and install under-slab insulation.
  • Start forming and other preparations for concrete floor pours.
  • Move Library shelving and layout new pathway to the Connector.  

SCHEDULED.

  • Pour the concrete “rat” slab, mechanical room slab and Connector slab.
  • Repair/replace floor beams and floor joists per architect’s details.
  • Building to be lowered once the concrete walls have cured and the floor joist system repairs are completed. (July)
  • Install Connector framing and Library roof tie-in. (August)
  • Refinish Town Hall floor. (late August)
Meghan Foley