TOWN HALL PROJECT UPDATE – WEEK 12
ACCOMPLISHED THIS WEEK
- Finished final grading in mechanical room floor.
- Finished installing floor beam support columns.
- Installed crawl space sump pump and piping.
- Installed crawl space floor vapor barrier and insulation.
NEXT WEEK
- Install underfloor plumbing piping in Connector.
- Final grade Connector Room floor and install under-slab insulation.
- Start forming and other preparations for concrete floor pours.
- Move Library shelving and layout new pathway to the Connector.
SCHEDULED.
- Pour the concrete “rat” slab, mechanical room slab and Connector slab.
- Repair/replace floor beams and floor joists per architect’s details.
- Building to be lowered once the concrete walls have cured and the floor joist system repairs are completed. (July)
- Install Connector framing and Library roof tie-in. (August)
- Refinish Town Hall floor. (late August)