Wilmot Town Hall Update – Week 11, May 27, 2024

 TOWN HALL PROJECT UPDATE – WEEK 11

ACCOMPLISHED THIS WEEK

  • Finished crawl space final grading.
  • Started to install stone and concrete piers in the main crawl space. (see picture)
    • NOTE: Yes, pier heights vary due to existing beam support details.
  • Equipment problems caused a delay in crawl space preparation.

NEXT WEEK

  • Finish final grading in mechanical room and Connector floors.
  • Finish installing floor beam support columns.
  • Install underfloor plumbing piping.
  • Install crawl space floor vapor barrier and insulation.
  • Move Library shelving and layout new pathway to the Connector.  

SCHEDULED.

  • Pour the concrete “rat” slab, mechanical room slab and Connector slab.
  • Repair/replace floor beams and floor joists per architect’s details.
  • Building to be lowered once the concrete walls have cured and the floor joist system repairs are completed. (July)
  • Install Connector framing and Library roof tie-in. (August)
  • Refinish Town Hall floor. (late August)
Meghan Foley