 TOWN HALL PROJECT UPDATE – WEEK 10

ACCOMPLISHED THIS WEEK

  • Installed perimeter insulation.
  • Started final grading the crawl space, mechanical room, and Connector floors. (see pictures)

NEXT WEEK

  • Finish final grading the crawl space, mechanical room, and Connector floors.
  • Install floor beam support columns.
  • Install underfloor plumbing piping.

SCHEDULED.

  • Install floor slab insulation and vapor barrier.
  • Pour the concrete “rat” slab, mechanical room slab and Connector slab.
  • Repair/replace floor beams and floor joists per architect’s details.
  • Building to be lowered once the concrete walls have cured and the floor joist system repairs are completed. (July)
  • Install Connector framing and Library roof tie-in. (August)
  • Refinish Town Hall floor. (late August)