TOWN HALL PROJECT UPDATE – WEEK 33 – October 28, 2024 (no week 32 report)
ACCOMPLISHED THIS WEEK
- Installed drywall in Connector.
- Installed old Safe door and new walls at old Safe area.
- Parking lot and N. Wilmot Road paving was rescheduled. Road was reclaimed on 11/1/24.
- Siding repairs continued.
- Topsoil installation finished.
NEXT WEEK
- Parking lot and N. Wilmot Road paving scheduled for November 7th. Road closure possible.
- Drywall finishing in Connector.
- Town Hall exterior walls to be insulated.
SCHEDULED.
- Connector flooring (November 11th – 13th)
- NOTICE: The electrical contractor was not responding to scheduling needs and has been replaced. Therefore, the restrooms will not be completed for the upcoming November 5th election. The temporary restrooms will remain.