Town Hall Project

Minutes and Agendas
Scopes of Work
Bid Advertisements
Schedule
Wilmot Town Hall Raising and Renovation
The restoration project has begun! Our Project Director, Jeff Gill will be providing updates for residents with weekly reports to be posted on this website. These updates will be able to be found via the Town Projects link on the home page of the website. This week we are posting via the newsletter so folks are aware of what is happening.

WEEK 1, March 18, 2024
ACCOMPLISHED THIS WEEK
- Furniture the equipment moved out of the hall by Highway Department.
- Erosion and soil controls installed.
- Topsoil stripped and stockpiled.
- Concrete and general waste dumpsters delivered.
- Portable restroom delivered for construction workers and one for Library use.
- Construction fencing installed.
- Temporary ramp installed a Library front entrance.
- Town Hall furnaces disconnected.
- Storage box delivered to 10 North Wilmot Rd
- Temporary barrier installed at 10 North Wilmot Rd to segregate area for construction.
NEXT WEEK
- Disconnection of Library boiler, hot water heater, pressure tank, etc.
- Disconnection of Town Hall electric service by NH COOP.
- Propane tank disconnected, emptied and tank removal by Irving Energy.
- Install isolation wall at bottom of Library ramp.
- Remove restroom fixtures.
- Start demolition of Town Hall/Library connector interior.
SCHEDULED
- Demolition of connector and Town Hall Safe in April.
- Raising Town Hall sequence to start first week in May.

WEEK 2 – March 25, 2024
ACCOMPLISHED THIS WEEK
- Disconnection of Library boiler, hot water heater and Town Hall Furnaces. Boiler and hot water heater will not be reused. Furnaces are stored for reinstallation later.
- Disconnection of Town Hall electric service by NH COOP.
- Install isolation wall at Library ramp. (It was decided to construct the wall around the entire ramp to eliminate disruption to Library operations when the ramp is filled with concrete later in the schedule.) (see picture)
- Start selective demolition of Connector interior. (doors, shelving, hardware, etc.)
- Demolished the floor above the Safe to verify concrete thickness on top and sidewalls. (see picture)
- Removed the carpeting in the Supervisors of the Checklist Office. (see picture)
INTERESTING DISCOVERY
- Once the floor coverings in the SOC office and upstairs above the Safe were removed we found 6” painted soft wood boards installed perpendicular to the floor joist. Further investigation will determine if this flooring was originally installed in the Town Hall main room. The current Town Hall flooring is maple installed parallel to the floor joist which was an uncommon installation technique in 1906 when the building was constructed.
NEXT WEEK
- The propane tank is to be disconnected, emptied and tank removed by Irving Propane. New tank to be installed later. (rescheduled to April 4th due to 18” snow)
- Remove restroom fixtures and pressure tank. (rescheduled due to 18” snow)
- Install temporary electric panel for use by the construction contractors.
- Continue selective demolition of the Connector to identify Creativity Lab electric wiring to be reconnected later.
- Protection and securing of the Town Hall scenery drapes on April 4th.
SCHEDULED
- Demolition of Connector and Town Hall Safe to start April 8th.
- Raising Town Hall sequence to start first week in May. (maybe sooner)
Many thanks to Mr. Phillips, who lives next to the church, for bringing down his large snow blower on Monday to remove the 18” of snow from the construction area!

WEEK 3 – April 1, 2024
ACCOMPLISHED THIS WEEK
- Temporary electric outlets installed for use by the construction contractors.
- Continued selective demolition of the Connector to identify Creativity Lab electric wiring.
- Removed snow from Site…again.
NEXT WEEK
- Remove restroom fixtures and pressure tank. (rescheduled due to snow)
- Start demolition to remove the Safe and Connector.
- Reconnect Library lighting circuits that were fed from the Connector subpanel.
- Protection and securing of the Town Hall scenery drapes. (awaiting confirmation)
SCHEDULED.
- The propane tank is to be disconnected, emptied and tank removed by Irving Propane. New tank to be installed later. (Rescheduled due to 2nd snowstorm, date not yet confirmed by Irving)
- Raising Town Hall sequence to start first week in May. (maybe sooner)

WEEK 4 – April 8, 2024
ACCOMPLISHED THIS WEEK
- Removed restroom fixtures and pressure tank.
- Safe (see picture) and Connector dormer demolished. Connector interior demo started.
- Started reconnecting Library lighting circuits that were fed from the Connector subpanel.
- Propane tank removed.
NEXT WEEK
- Finish Connector demo and waterproof adjoining Library and Creativity Lab walls once Connector roof is removed.
- Finish reconnection of Library electric circuits fed from Connector subpanel.
- Protection and securing of the Town Hall scenery drapes. (awaiting confirmation)
- Architect to visit site to start design of the higher roof over Library. (Library roof adjoining the Creativity Lab will need to be raised so ridge line matches new elevation of raised Lab.)
SCHEDULED.
- Rigger to move in equipment the week of April 22nd.
- Raising Town Hall sequence to start first week in May.
- Footer and crawl space excavation in May immediately after building is raised.
- Concrete foundation walls to start in late May immediately after footer excavation.
INTERESTING DISCOVERY The front wall of the Safe was 2 ft. thick but the remaining walls and ceiling were only 6” to 8” thick.

WEEK 5, April 15, 2024
NOTICE
- Our rigger now wants to come on Monday, April 22nd. This will mean the lot at 14 N Wilmot will be very limited for use by anyone except construction workers as we will be trucking and stockpiling soils across the street.
- The stakes that identify limits of construction will again be installed to identify the “keep out” area.
- Once the soil stockpiling is finished, the “keep out” area will be reduced.
- Lift could start Thursday, but it depends on the challenges encountered with installing the lifting beams under the building.
ACCOMPLISHED THIS WEEK
- Connector interior demolished. (see pictures)
- Finished reconnecting Library lighting circuits that were fed from the Connector subpanel.
- Town Hall and Library drapes removed for cleaning.
- Architect visited the site and working on Connector design and roof build back details.
NEXT WEEK
- Finish Connector demo and waterproof adjoining Library and Creativity Lab walls once Connector roof is removed.
- Protection and securing of the Town Hall scenery drapes.
- Rigger to move in Monday to set lifting beams and jacks.
SCHEDULED
- Footer and crawl space excavation in May immediately after building is raised.
Concrete foundation walls to start in late May immediately after footer excavation.

WEEK 6 – April 22, 2024
ACCOMPLISHED THIS WEEK
- Finished the Connector demo and waterproofed the adjoining Library and Creativity Lab walls.
- Protected the Town Hall scenery drapes and secured the support structure. (see picture)
- Building lifted. Large rocks were removed. (see pictures)
NEXT WEEK
- The remaining large rocks are to be removed.
- Building footer excavation.
- Concrete contractor to mobilize in preparation of pouring footers.
- Meeting architect to determine the scope of work needed to fix the floor joist system.
SCHEDULED.
- Form and pour concrete walls once footers are poured. (Mid-May)
- Install crawl space perimeter insulation once concrete walls are poured and forms striped.
- Final grade the crawl space floor then pour the concrete “rat” slab.
- Building to be lowered once the concrete walls have cured and the floor joist system repairs are completed. (July)

WEEK 7 – April 29, 2024
ACCOMPLISHED THIS WEEK
- The remaining large rocks were removed.
- Building footers excavated. (see picture)
- Concrete contractor mobilized and are forming footers. (see picture)
- Met with architect and detailed the scope of work required to fix the floor joist system.
NEXT WEEK
- Pour footer concrete.
- Set forms for concrete foundation walls.
SCHEDULED.
- Pour concrete walls. (Mid-May)
- Install crawl space perimeter insulation once concrete walls are poured and forms striped.
- Final grade the crawl space floor then pour the concrete “rat” slab.
- Repair/replace floor beams and floor joists per architect’s details.
- Building to be lowered once the concrete walls have cured and the floor joist system repairs are completed. (July)

WEEK 8 – May 6, 2024
ACCOMPLISHED THIS WEEK
- Poured concrete footers and forms striped. (see pictures)
- Forms for concrete foundation walls started. (see picture)
NEXT WEEK
- Finish forming wall pockets and stone veneer ledge.
- Pour concrete walls.
- Strip concrete wall forms.
SCHEDULED.
- Install perimeter insulation.
- Final grade the crawl space, mechanical room and Connector floors.
- Install floor slab insulation and vapor barrier.
- Pour the concrete “rat” slab, mechanical room slab and Connector slab.
- Repair/replace floor beams and floor joists per architect’s details.
- Building to be lowered once the concrete walls have cured and the floor joist system repairs are completed. (July)

WEEK 9 – May 13, 2024
ACCOMPLISHED THIS WEEK
- Finished forming wall pockets and stone veneer ledge.
- Poured concrete walls.
- Striped concrete wall forms.
NEXT WEEK
- Install perimeter insulation.
- Start final grading the crawl space, mechanical room and Connector floors.
SCHEDULED.
- Finish final grading the crawl space, mechanical room and Connector floors.
- Install floor slab insulation and vapor barrier.
- Pour the concrete “rat” slab, mechanical room slab and Connector slab.
- Repair/replace floor beams and floor joists per architect’s details.
- Building to be lowered once the concrete walls have cured and the floor joist system repairs are completed. (July)

WEEK 10 – May 20, 2024
ACCOMPLISHED THIS WEEK
- Installed perimeter insulation.
- Started final grading the crawl space, mechanical room, and Connector floors. (see pictures)
NEXT WEEK
- Finish final grading the crawl space, mechanical room, and Connector floors.
- Install floor beam support columns.
- Install underfloor plumbing piping.
SCHEDULED.
- Install floor slab insulation and vapor barrier.
- Pour the concrete “rat” slab, mechanical room slab and Connector slab.
- Repair/replace floor beams and floor joists per architect’s details.
- Building to be lowered once the concrete walls have cured and the floor joist system repairs are completed. (July)
- Install Connector framing and Library roof tie-in. (August)
- Refinish Town Hall floor. (late August)

WEEK 11 – May 27, 2024
ACCOMPLISHED THIS WEEK
- Finished crawl space final grading.
- Started to install stone and concrete piers in the main crawl space. (see picture)
- NOTE: Yes, pier heights vary due to existing beam support details.
- Equipment problems caused a delay in crawl space preparation.
NEXT WEEK
- Finish final grading in mechanical room and Connector floors.
- Finish installing floor beam support columns.
- Install underfloor plumbing piping.
- Install crawl space floor vapor barrier and insulation.
- Move Library shelving and layout new pathway to the Connector.
SCHEDULED.
- Pour the concrete “rat” slab, mechanical room slab and Connector slab.
- Repair/replace floor beams and floor joists per architect’s details.
- Building to be lowered once the concrete walls have cured and the floor joist system repairs are completed. (July)
- Install Connector framing and Library roof tie-in. (August)
- Refinish Town Hall floor. (late August)

WEEK 12 – June 3, 2024
ACCOMPLISHED THIS WEEK
- Finished final grading in mechanical room floor.
- Finished installing floor beam support columns.
- Installed crawl space sump pump and piping.
- Installed crawl space floor vapor barrier and insulation.
NEXT WEEK
- Install underfloor plumbing piping in Connector.
- Final grade Connector Room floor and install under-slab insulation.
- Start forming and other preparations for concrete floor pours.
- Move Library shelving and layout new pathway to the Connector.
SCHEDULED.
- Pour the concrete “rat” slab, mechanical room slab and Connector slab.
- Repair/replace floor beams and floor joists per architect’s details.
- Building to be lowered once the concrete walls have cured and the floor joist system repairs are completed. (July)
- Install Connector framing and Library roof tie-in. (August)
- Refinish Town Hall floor. (late August)

WEEK 13 – June 10, 2024
ACCOMPLISHED THIS WEEK
- Installed underfloor plumbing piping in Connector.
- Poured foundation wall left out for equipment access. (see picture)
- NOTE: Due to a concrete pump truck scheduling delay, the crawl space floor will not be poured until next Friday
NEXT WEEK
- Pour Crawl Space floor (rat slab)
- Move Library shelving and layout new pathway to the Connector.
SCHEDULED.
- Repair/replace floor beams and floor joists per architect’s details.
- Building to be lowered once the concrete walls have cured and the floor joist system repairs are completed. (July)
- Install Connector framing and Library roof tie-in. (August)
- Refinish Town Hall floor. (late August)

WEEK 14 – June 17, 2024
ACCOMPLISHED THIS WEEK
- Poured Crawl Space “rat slab” floor (see picture)
NEXT WEEK
- Start repair/replacement of floor beams and floor joists per architect’s details.
SCHEDULED.
- Move Library shelving and layout new pathway to the Connector.
- Building to be lowered once the concrete walls have cured and the floor joist system repairs are completed. (July)
- Install Connector framing and Library roof tie-in. (August)
- Refinish Town Hall floor. (late August)

WEEK 15 – June 24, 2024
ACCOMPLISHED THIS WEEK
- Started repair/replacement of floor beams and floor joists per architect’s details.
NEXT WEEK
- Finish repair/replacement of floor beams and floor joists.
SCHEDULED.
- Move Library shelving and layout new pathway to the Connector.
- Building to be lowered once the concrete walls have cured and the floor joist system repairs are completed. (Possibly 2nd week in July)
- Patch lifting beam pockets.
- Finish floor system repairs.
- Reinstall windows.
- Install Connector framing and Library roof tie-in. (August)
- Refinish Town Hall floor. (late August)

WEEK 16 – July 1, 2024
ACCOMPLISHED THIS WEEK
- Continued repair/replacement of floor beams and floor joists per architect’s details.
NEXT WEEK
- Finish repair/replacement of floor beams and floor joists.
- Move Library shelving and layout new pathway to the Connector
SCHEDULED.
- The building is scheduled to be lowered on Monday July 15th. Exact timing will be communicated next week.
- Patch lifting beam pockets.
- Finish floor system repairs.
- Reinstall windows.
- Pour Connector floor.
- Install Connector framing and Library roof tie-in. (August)
- Refinish Town Hall floor. (late July)
NOTE: As planned, the Town Hall and Creativity Lab should be ready to be used for the September 10th Primary Election. However, the Connector finishes will not be completed at that time, therefore portable restrooms will be available for Poll workers and Library staff use.

Week 17 – July 8, 2024
ACCOMPLISHED THIS WEEK
- Completed the repair/replacement of floor beams and floor joists per architect’s details. It has been determined that some exterior beams and the replacement of the floor where the Safe was located will be completed after the building is lowered.
- Move library shelving and layout new pathway to the Connector

WEEK 18 – July 15, 2024
ACCOMPLISHED THIS WEEK
- The building was lowered down onto the new foundation walls.
- Restored windows were delivered.
- Backfilling the foundation was started. (see picture)
NEXT WEEK
- Foundation backfilling will be finished to rough grade elevations.
- Restored windows will be reinstalled.
- Connector floor area will be graded and insulated in preparation for the concrete floor slab.
SCHEDULED.
- Patch lifting beam pockets.
- Finish floor system repairs.
- Pour Connector floor.
- Install Connector framing and Library roof tie-in. (August)
- Refinish Town Hall floor. (late July)
NOTE: As planned, the Town Hall and Creativity Lab should be ready to be used for the September 10th Primary Election. However, the Connector finishes will not be completed at that time, therefore Portable restrooms will be available for Poll workers and Library staff use.

WEEK 19 – July 22, 2024
ACCOMPLISHED THIS WEEK
- Foundation backfilling finished to rough grade elevations.
- Perimeter drain installed.
- Reinstallation of restored windows started. (see picture)
- Grade raised at front door for easier access. (NOTE: The slope is steep until the parking area is raised, see picture)
- New well supply pipe from well casing to the Connector installed.
- Electric service line reconnected to building.
NEXT WEEK
- Finish reinstalling windows.
- Connector floor area will be graded and insulated in preparation for the concrete floor slab.
- Patch lifting beam pockets.
- Start the final floor system repairs.
SCHEDULED.
- Pour Connector floor.
- Install Connector framing and Library roof tie-in. (August)
- Refinish Town Hall floor. (August)
NOTE: As planned, the Town Hall and Creativity Lab should be ready to be used for the September 10th Primary Election. However, the Connector finishes will not be completed at that time, therefore Portable restrooms will be available for Poll workers and Library staff use.

WEEK 20 – July 29, 2024
ACCOMPLISHED THIS WEEK
- Reinstallation of restored windows finished.
- New Electric meter installed. Electric service now restored to Town Hall.
- Lifting beam pockets in foundation formed and ready for infill concrete. (see picture)
- Beams around the old Safe replaced.
NEXT WEEK
- Connector floor area will be graded and insulated in preparation for the concrete floor slab.
- Pour. lifting beam pockets.
- Exterior grades will be established, and Town Hall front door slab formed.
SCHEDULED.
- Pour Connector floor.
- Install Connector framing and Library roof tie-in.
- Reinstall Town Hall furnaces.
- Refinish Town Hall floor.
NOTE: As planned, the Town Hall and Creativity Lab should be ready to be used for the September 10th Primary Election. However, the Connector finishes will not be completed at that time, therefore Portable restrooms will be available for Poll workers and Library staff use.

WEEK 21 – August 5, 2024
ACCOMPLISHED THIS WEEK
- Connector floor area graded and insulated in preparation for the concrete floor slab. (see picture)
- Temporary Stage curtain supports removed.
- The Town Hall floor was cleared in preparation for floor refinishing.
- Exterior grades verified.
NEXT WEEK
- Pour Connector floor.
- Pour lifting beam pockets.
- Start Connector framing.
- Engage architect to determine final exterior grades for parking lot.
SCHEDULED.
- Reinstall Town Hall furnaces.
- Refinish Town Hall floor.
NOTE: As planned, the Town Hall and Creativity Lab should be ready to be used for the September 10th Primary Election. However, the Connector finishes will not be completed at that time, therefore Portable restrooms will be available for Poll workers and Library staff use.

WEEK 22 – August 12, 2024
ACCOMPLISHED THIS WEEK
- Poured Connector floor.
- Poured lifting beam pockets.
- Town Hall floor sanding started. (see picture)
NEXT WEEK
- Install new propane tank and new underground propane lines.
- Start Connector framing.
- Engage architect to determine final exterior grades for parking lot.
- Reinstall Town Hall furnaces.
- Refinish Town Hall floor.
- Start electrical upgrades.
SCHEDULED.
- Remove temporary barricade in Library (week of September 2nd)
- Finish Electric
NOTE: As planned, the Town Hall and Creativity Lab should be ready to be used for the September 10th Primary Election. However, the Connector finishes will not be completed at that time, therefore Portable restrooms will be available for Poll workers and Library staff use.

WEEK 23 – August 19, 2024
ACCOMPLISHED THIS WEEK
- Installed new propane tank and new underground propane lines.
- Started Connector framing. (see picture)
- Engaged architect to determine final exterior grades for parking lot.
- Reinstalled Town Hall furnaces.
- Installed septic system vent pipe.
NEXT WEEK
- Continue with Connector framing.
- Complete refinishing of the Town Hall floor.
- Electrical upgrades to reconnect the Creativity Lab.
- Reconnect water pressure tank.
- Install concrete forms for Town Hall front pad.
- Meet with architect and Town Hwy Dept to agree parking lot elevations.
SCHEDULED.
- Pour Town Hall front pad.
- Remove temporary barricade in Library (week of September 2nd)
- Finish Electric connections for Connector/Creativity Lab.
- Finish Safe floor framing.
- Town Hall and Creativity Lab cleaning.
- Bring election booths, tables, chairs, etc. back from storage.
- Remove storage box.
- Remove security fencing.
NOTE: As planned, the Town Hall and Creativity Lab should be ready to be used for the September 10th Primary Election. However, the Connector finishes will not be completed at that time, therefore Portable restrooms will be available for Poll workers and Library staff use.

WEEK 24 – August 26, 2024
ACCOMPLISHED THIS WEEK
- Finished Connector framing. (see pictures)
- Connector electrical rough-in started.
- Connector plumbing rough-in started.
- Met with architect and Town Hwy Dept to agree parking lot elevations.
- Town Hall main room, stage and SOC Office floor refinishing completed. (see pictures)
- Propane tank filled and connected to Town Hall furnaces.
- Creativity Lab deck platform installed.
NEXT WEEK
- Reconnect water pressure tank.
- Install concrete forms for Town Hall front pad and pour pad.
- Finish floor framing in old Safe area.
- Remove temporary barricade in Library.
- Town Hall and Creativity Lab cleaning. (September 5th)
- Move election materials back into Town Hall. (start September 6th)
- Bring election booths, tables, chairs, etc. back from storage. (start September 6th)
- Remove storage box.
- Remove security fencing.
- Install temporary ramps to Town Hall and Creativity Lab.
SCHEDULED.
- Complete Connector plumbing and electric rough-ins.
- Insulate Connector.
- Install drywall in Connector.
- New electrical outlets in Town Hall.
NOTE: As planned, the Town Hall and Creativity Lab should be ready to be used for the September 10th Primary Election. However, the Connector finishes will not be completed at that time, therefore Portable restrooms will be available for Poll workers and Library staff use.

WEEK 25 – September 2, 2024
ACCOMPLISHED THIS WEEK
- Reconnected water pressure tank.
- Installed hot water tank for Kitchen.
- Installed concrete forms for Town Hall front pad and pour pad.
- Finished floor framing in old Safe area.
- Removed temporary barricade in Library.
- The Town Hall and Creativity Lab cleaned.
- Started to move election materials back into the Town Hall.
- Removed storage box.
- Removed security fencing.
- Installed temporary ramps at the Town Hall and Creativity Lab. (see picture)
NEXT WEEK
- Bring election booths, tables, chairs, etc. back from storage.
- Install railings on the Town Hall entrance. Pad.
SCHEDULED.
- Complete Connector plumbing and electric rough-ins.
- Insulate Connector.
- Install drywall in Connector.
- New electrical outlets in Town Hall.
NOTE: As planned, the Town Hall and Creativity Lab WILL be ready to be used for the September 10th Primary Election. However, the Connector finishes will not be completed at that time, therefore Portable restrooms will be available for Poll workers and Library staff use.
WEEK 26 – September 9, 2024
ACCOMPLISHED THIS WEEK
- Bring election booths, tables, chairs, etc. back from storage.
NEXT WEEK
- Due to the election and Town Meeting on the 17th, work is limited until week of 9/23/24.
SCHEDULED.
- Complete Connector plumbing and electric rough-ins.
- Insulate Connector.
- Install drywall in Connector.
- New electrical outlets in Town Hall.
NOTE: As planned, the Town Hall and Creativity Lab WERE used for the September 10th Primary Election!
WEEK 27 – September 16, 2024
ACCOMPLISHED THIS WEEK
- Per Week 26 Update – Due to the election and Town Meeting on the 17th, work is limited until the week of 9/23/24.
NEXT WEEK
- Complete Connector plumbing and electric rough-ins.
- Install foundation veneer stone.
- Start flooring at the Foyer and Safe areas.
SCHEDULED.
- Apply additional finish coat to Town Hall Floor.
- Insulate Connector.
- Install drywall in Connector.
- New electrical outlets in Town Hall.
- Parking lot and Site grading (October 11 – 20) NOTE: Also, limited parking across the street due to material stockpiles.
- Connector flooring (October 21-23)
WEEK 28 – September 23, 2024
ACCOMPLISHED THIS WEEK
- Due to the election and Town Meeting on the 17th, work as stalled due to unavailability of contractors.
- Installed foundation veneer stone.
NEXT WEEK
- Complete Connector plumbing and electric rough-ins.
- Start flooring at the Foyer and Safe areas.
- Finish Connector electrical rough-in.
- Finish Connector porch framing.
SCHEDULED
- Apply additional finish coat to Town Hall Floor.
- Insulate Connector.
- Install drywall in Connector.
- New electrical outlets in Town Hall.
- Parking lot and Site grading (October 11–20) NOTE: Also, limited parking across the street due to material stockpiles.
- Connector flooring (October 21-23)
WEEK 29 – September 30, 2024
ACCOMPLISHED THIS WEEK
- Due to the election and Town Meeting on the 17th, work as stalled due to unavailability of contractors. NOTE: Contractors now verified to restart next week.
- Install Foyer and old Safe area floor
NEXT WEEK
- Complete Connector plumbing and electric rough-ins.
- Finish Connector electrical rough-in.
- Finish Connector porch and Connector interior framing
- Start reroofing Town Hall and Connector
- Apply additional finish coat to Town Hall Floor.
SCHEDULED.
- Insulate Connector.
- Install drywall in Connector.
- New electrical outlets in Town Hall.
- Parking lot and Site grading (October 11 – 20) NOTE: Also, limited parking across the street due to material stockpiles.
- Connector flooring (October 21-23)
07
